Timeline
2016 - 2018
-
Facility designed by Greenbrier East students & mentors.
-
Development & operational expense forecasts created.
-
Feasibility assessment conducted.
-
Initial public presentations delivered & met with support.
-
Fundraising efforts initiated.
2019
-
Director of Community & Donor Engagement hired Q1.
-
Conduct site survey & finalize land lease with the State Fair of West Virginia.
-
Increase community awareness & fundraising efforts.
-
Pursue local, regional & nationwide grant opportunities.
-
Select pool consultant.
-
Begin design development & construction documents.
-
Complete capital commitment phase.
2020
-
Bid out construction project.
-
Select contractors for development.
-
Begin facility construction efforts.
-
Develop detailed membership models.
-
Initiate membership marketing and advertising efforts.
-
Grow membership roster across all categories.
2021
-
Hire key management staff.
-
Develop detailed facility programming.
-
Complete facility construction & interior installation.
-
Hire hourly staff members & conduct training programs.
-
Continue growing membership roster.
-
Open facility to our membership.